Las Tunas, Cuba.- When exchanging views with investor and builders, Carlos Arias Sobrino, director of the Electric Company in the province, reported that they work on the eight objects included in the general project, which goes as scheduled.
Among these, he mentioned the foundations of the wind turbine bases, roads, for underground electrical networks, the substation and the 110 kv line.
After noting that the 34 bases are in different phases of execution, Arias Sobrino highlighted the effort and quality achieved in the foundry of the first two platforms.
At this moment, the enlistment of a third base is accelerated, with the objective of cast it next Wednesday.
When abounding on that particular, Carlos Manuel Quesada Borges, general director of the Company of Construction and Assembly in Las Tunas, valued of successful the casting of steel and concrete in the first two bases, with a level of resistance over what was planned.
"Due to the level of experience achieved, we plan to close this year with more than 20 completed bases and deliver "La Herradura 1" in March 2020, approximately. We have the aggregates, the steel and the workforce is ready to comply with the task," assured Quesada.
Arias Sobrino pointed out that "we consider that we are advancing according to the possibilities, but from the precisions made today by the Commander, we reconsider some variants, with the intention of save resources and achieve greater efficiency and quality.
Along with Ramiro Valdés Menéndez were the member of the Central Committee of the Party and its first secretary in Las Tunas, Ariel Santana Santiesteban, and Jaime Ernesto Chiang Vega, president of the Provincial Assembly of the People's Power.